Shell Oil Company ADA Construction Requirements
Retail
ADA Program
The Project
Shell required ADA enhancements to over 500 existing gasoline stations. QPM was engaged to review the plans and scope of work for compliance, request and review bids, prepare site-specific budgets and schedules, inspect upon completion to ensure compliance, review payment applications and review the project closeout package.
The QPM Solution
This project was complicated by significant discrepancies between the Consent Decree and the original scope of work. Once QPM had identified these discrepancies, special attention was given to each site in order to ensure compliance with the Consent Decree – in some cases even requirement scope of work be redone and re-permitted.
The Results
QPM’s diligent interpretation of the Consent Decree requirements, along with detailed pre-construction walks and post-construction documentation, ensured full compliance with the legal agreement. This reduced the possibility of rework and ensured timeline completion of the program.